TCS Automated Warehouse
Implement OT Network
The success of this large-scale project, being the first of its kind deployed in Vietnam, demonstrates SongNam's excellent project management capability when working with domestic partners like ITD and foreign partners like Siemens.
PROJECT INFO
The automated warehouse project at Tan Son Nhat Airport is a large and complex project. Tan Son Nhat is the first airport in Vietnam to install and operate this modern and automated warehouse facility. The project is carried out by ITD and Siemens as the main contractors, while SongNam is a subcontractor, responsible for installing the signal cable system, all sensors, control equipment, and the information technology system to operate the warehouse.
Project Scale:
- Pulling 25,000m of signal and control cables.
- Installing over 500m of cable trays.
- Terminating and connecting over 1,200 operating sensor devices.
- Establishing a fiber optic cable system, network cables, and a wireless system for the IT network infrastructure to manage the warehouse according to industrial standards.
- The control system installation project was completed within 4 months.